Quote:
Originally Posted by nealtw
All the pictures with the system above show concrete patch of only about a inch and a half. So if the basement was finished with a wall built inside the foundation, the weight of the wall will be suppoted by this plastic pipe. If the wall was put in tight as meny are and flexing in the floor above would apply more pressure on this pipe and the joint of the new and old concrete.
|
I had considered that, so to mitigate this issue I was planning to build the wall about 4 - 6 inches away from the wall.
Hmmm...
Does anyone know of a better product/method of doing this?