Bare with me as I try and word these questions and ask them the best I can. I have concrete block for walls. There will be sill plate sitting on top of the block for the trusses to sit on. There will be a concrete pad floor poured. My question is to be able to determine where the top of the pad will be pored then shouldnt I measure from where the top of the sill plate is (where the trusses sit)? If I measure from the top of the sill plate just where the trusses sit on them down exactly 8' then that is where the concrete pad should be poured to...correct ?
I want my walls and drywall to come out good without cutting as much (if possible)
Wouldnt I be attaching the top side of the drywall to the "side" of the 2X4 that is straight across and horizontally even with the sill plate sitting on the block ?
For my walls I know there would be a treated 2X4 on the concrete and I believe a 2X4 nailed to the bottom of the trusses just even across from the sill plate (?) and I believe they sell 2X4's that are 92 5/8" long that wouls fit in between these two boards but I want to make sure I have the correct 8' distance from top to bottom.
Does is sound like Im on the right track



__________________

Last edited by Mudball; 06-17-2006 at 04:50 PM.
Mudball is offline  
 
Reply With Quote Quick reply to this message
Old 06-17-2006, 06:17 PM  
inspectorD
Housebroken
HRT_MODERATOR.png
 
inspectorD's Avatar
 
Join Date: Dec 2005
Location: Litchfield, CT
Posts: 4,054
Liked 122 Times on 102 Posts
Likes Given: 286

Default Hmmm.

If I understand what you said....yes.
Also ...is the concrete floor going to be built up at all?
The truss's should have some 3/4 inch straping nailed to the bottom coard for sheetrock at 16" on center. This will help the rock not to crack due to span's and uplift of the truss system.

Got all that???

What are you building?



__________________

Just My
Made in the

inspectorD is offline  
 
Reply With Quote Quick reply to this message
Old 06-17-2006, 06:47 PM  
Square Eye
Senior Member
 
Square Eye's Avatar
 
Join Date: Jan 2006
Posts: 1,273
Liked 4 Times on 4 Posts

Default

97" is where you want to end up. 92 5/8" + (1 1/2 x3 =)4 1/2 = 97 1/8" building standard when stick framing. You will have to make some cuts somewhere or stack some 2x's to make up the difference.

The reason for the extra inch is that you want the extra inch to allow for 1/2 " of drywall ceiling and 1/2" off of the floor to keep the drywall up off of the floor to keep moisture from wicking up the wallboards.

__________________

[URL="http://www.houserepairtalk.com/announcement.php?f=39&a=6"][size=3]The Ten Commandments of House Repair Talk[/size][/URL]



[URL="http://home.bellsouth.net/p/s/community.dll?ep=16&groupid=289528&ck="]Square Eye's home page[/URL]

Square Eye is offline  
 
Reply With Quote Quick reply to this message
Old 06-17-2006, 07:02 PM  
inspectorD
Housebroken
HRT_MODERATOR.png
 
inspectorD's Avatar
 
Join Date: Dec 2005
Location: Litchfield, CT
Posts: 4,054
Liked 122 Times on 102 Posts
Likes Given: 286

Default Yup

My math sucks.... I was just adding the 3 plates a-s-suming they were there...I better pay more attention.

Square Eye...empty your message box willya..your full.
The edit my phopa here...

__________________

Just My
Made in the

inspectorD is offline  
 
Reply With Quote Quick reply to this message
Old 06-18-2006, 03:57 AM  
Mudball
Member
 
Join Date: May 2006
Posts: 53
Default

Thanks a whole bunch. Now I understand a lot better.
Just wondering though is it better to be too short and cut off whats needed or be too long and have to stack to make up the difference ? If you had to be closer to one way or the other then which would it be ?
Thanks again.

__________________
Mudball is offline  
 
Reply With Quote Quick reply to this message
Old 06-18-2006, 08:19 AM  
inspectorD
Housebroken
HRT_MODERATOR.png
 
inspectorD's Avatar
 
Join Date: Dec 2005
Location: Litchfield, CT
Posts: 4,054
Liked 122 Times on 102 Posts
Likes Given: 286

Default Me thinks you got it backwards...

Make them 1/4 " short and shim them into place at the top.
Easier to stand up the walls that way.

__________________

Just My
Made in the

inspectorD is offline  
 
Reply With Quote Quick reply to this message
Old 06-18-2006, 06:07 PM  
Mudball
Member
 
Join Date: May 2006
Posts: 53
Default

Thats sounds great. Thanks for the help. I guess a lot depends on the concrete pad contractor when that time comes.



__________________
Mudball is offline  
 
Reply With Quote Quick reply to this message
Reply


Quick Reply
Message:
Options

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter DIY Home Repair Forum Replies Last Post
Building Deck high off ground guyod General Home Improvement Discussion 10 03-02-2012 10:14 PM
High limit problem on Trane XE90 Garvey HVAC 1 11-10-2011 08:33 AM
rates per sq foot of various activities Will1987 Flooring 5 11-06-2006 03:54 PM