Originally Posted by BridgeMan View Post
Jumping in a bit late here, but I have to ask--exactly why are you considering slab-jacking? Is the interior of the house floor settled? If the intent is just to fill the void under the slab shown in the photo, that's easy to accomplish by a DIYer at considerably less expense than what you were quoted.
A little late but the chimney leaning was the reason for the mudjacking.


__________________
nealtw is offline  
 
Reply With Quote Quick reply to this message
Old 08-29-2013, 09:18 PM  
BridgeMan
Senior Member
 
BridgeMan's Avatar
 
Join Date: Aug 2011
Location: Cottage Grove, Oregon
Posts: 738
Liked 75 Times on 67 Posts

Default

Quote:
Originally Posted by nealtw View Post
A little late but the chimney leaning was the reason for the mudjacking.
Sorry, neal, but he didn't mention that he was trying to correct the slightly-tilted chimney by means of mud-jacking. His concern was the large void under the slab, not adjacent to the chimney.


__________________
BridgeMan is offline  
 
Reply With Quote Quick reply to this message
Old 08-29-2013, 09:59 PM  
BridgeMan
Senior Member
 
BridgeMan's Avatar
 
Join Date: Aug 2011
Location: Cottage Grove, Oregon
Posts: 738
Liked 75 Times on 67 Posts

Default

Quote:
Originally Posted by Bridger51 View Post
BridgeMan - I'm with you. I have a ranch style home in Florida that has the underside of the slab becoming exposed due to a the yard settling. . . . . but how exactly do I make sure all the air is removed from under my slab from the outside?? Today is the first time I noticed how bad it is. Not more than 1 inch of air, but it goes back under the slab at least 1 foot. . . . Can I use a poly compound myself? This should be a DiYer....IMO. BridgeMan if your out there, you seemed like this could be an easy fix.

I was thinking of using a loose concrete or poly and letting it settle under the house than burying that under the dirt, But do I have to keep everything from sticking out farther than the current slab? Will only a couple inches laterally create different problems in the future?
If all you're dealing with is only an inch of settlement, extending just a foot under the slab, why not go the cheap (and easy) way? Which in my opinion would be dry-packing a pre-packaged concrete mix into the voided areas, working from the outside, and starting in the middle of any given void and working outwards to enable entrapped air to escape. Hardest part would be hand-excavating temporary "work stations" in the adjacent soil, to provide space for working a tamper back and forth after you've dropped in a load of slightly-stiff (no more than 2" slump) concrete, preferably off of slightly-sloped, intermittent planks. Installing the planks with gaps between them will provide room for working your tamper in a horizontal plane. Use a 2 x 4 in the flat orientation for the tamper, rounding the edge you hold to avoid blisters.

Doing it this way is economical, probably less than $50 for bagged concrete, depending on the size and extent of your house's voids. Ten 80-lb. bags of mud will cover almost 100 feet of voids around the perimeter of the house, assuming an average thickness of 3/4". And there should be no extensions of your work beyond the existing slab, as you can finish the concrete flush with the slab edges with a hand float (resin or mag) if poured stiff enough.
__________________
BridgeMan is offline  
 
Reply With Quote Quick reply to this message
Old 08-29-2013, 10:29 PM  
nealtw
Contractor
 
Join Date: Nov 2010
Location: vancouver, b.c.
Posts: 10,226
Liked 838 Times on 749 Posts
Likes Given: 1456

Default

Quote:
Originally Posted by BridgeMan View Post
Sorry, neal, but he didn't mention that he was trying to correct the slightly-tilted chimney by means of mud-jacking. His concern was the large void under the slab, not adjacent to the chimney.
So let's go over the problem; A slab, maybe a patio or garage or carport, who knows, laid on dirt, soft dirt. If this was errosion, where did the dirt go.

It went down, settled, As the problem may have been isolated to this area and the void is what needs to be dealt with mudjacking would fill the void and raise the slab back to level. As stated, that still leaves the problem of frost protection and no footing.
Was there something you wanted to add to that.
__________________
nealtw is offline  
 
Reply With Quote Quick reply to this message
Reply


Quick Reply
Message:
Options

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter DIY Home Repair Forum Replies Last Post
Slab foundation with void under jet tub para58d Framing and Foundation 1 03-08-2012 05:08 PM
Concrete Slab home; void under bathtub thegogetter222 Framing and Foundation 13 10-26-2011 08:11 AM
Driveway Erosion Parrothead Garden and Lawncare 4 02-15-2011 07:06 PM
Filling in a void with concrete head-first Bricks, Masonry and Concrete 13 11-10-2010 08:09 AM
foundation erosion tputnam Bricks, Masonry and Concrete 0 09-27-2006 12:35 PM