Old 08-27-2012, 07:22 PM  
D725A
Member
 
Join Date: Feb 2010
Posts: 84
Liked 4 Times on 4 Posts

Default Questions on Roof Job in Progress

Having an architectural shingle roof installed in NYS. Grace Shingle-mate is the underlayment. For some reason they started with that at midroof and worked their way up, then installed the Grace ultra ice/water shield from eave up. Seems they were able to keep the overlaps always top over bottom as you look from peak to eave. Usually from what I know they go from bottom to top. I noticed there were a few areas where light shows through the Shingle-mate; probably due to the staples hitting a space between the old tongue and groove decking. Should i have them patch that over with some pieces of tape or water shield or is that normal?

Where a porch hip roof meets a vinyl wall, can they install the proper flashing without temporarily removing the bottom part of the vinyl wall?

Shall I assume that no black roofing cement should be used (tar?) on the chimney? Contract calls for step, apron flashing and back pan around chimney. Counter flashing against chimney to ensure watertight area, copperwork soldered etc. Where the upper copper edge is placed in between bricks pointing mortar should be used yes?

thanks. I ask all this because some things have been done differently than I was told they would so then I feel I have to pay more attention.



__________________
D725A is offline  
 
Reply With Quote Quick reply to this message
Old 08-27-2012, 11:46 PM  
oldognewtrick
Moderator
HRT_MODERATOR.png
 
oldognewtrick's Avatar
 
Join Date: Jul 2009
Location: Nashville, TN
Posts: 4,346
Liked 312 Times on 263 Posts
Likes Given: 109

Default

The ice and water shield should be installed horizontally along the eave up the roof, 3' past the interior wall if the roof has a slope 4/12 or greater. Then the Shingle Mate installed horizontally the rest of the way with ice and water picture framing the ridge and hips. The laps should always be the top sheet over the bottom sheet.

The vinyl siding and bottom "J" channel will have to be removed at the area closet to the roof to remove the old flashing and install the new.

We always install new step flashing against the brick chimney, then caulk the top of the flashing to the brick prior to fabricating new counter flashing and new top and bottom pans with ice and water shield on the cricket and chimney sides. This does not show when the installation is complete.



__________________
oldognewtrick is offline  
 
Reply With Quote Quick reply to this message
Old 08-28-2012, 09:43 PM  
nealtw
Senior Member
 
Join Date: Nov 2010
Location: vancouver, b.c.
Posts: 8,815
Liked 659 Times on 590 Posts
Likes Given: 1168

Default

Oldog didn't address the holes made with a stapler. I would think if you put it there as a last defence against water, having holes in it kinda goes against common sence.

__________________
nealtw is offline  
 
Reply With Quote Quick reply to this message
Old 09-04-2012, 07:39 PM  
D725A
Member
 
Join Date: Feb 2010
Posts: 84
Liked 4 Times on 4 Posts

Default

So the job is almost done; I'd say it came out OK. The underlayment could have been done more carefully, and they should have replaced more planks and with the kind of wood specified. The porch eave shingles--not pictured-- will have to be trimmed as they are over 2 inches over the drip edge.

One question I have is re: slotting the drip edge to allow it to accommodate the zip hangars which may allow in turn the drip edge to lean back closer to the rear wall of the gutter. In this case the gutters were re-installed after the drip edge was, so when they pushed up the rear gutter wall up behind the drip edge, they could only go up as far as the hangar screw. The angles the attached photos were taken at makes it difficult to see how far out the drip edge is bent forward. My main problem with this is not so much drip edge function or slight blocking of the gutter, but the space behind being a nice nesting place for bees etc, so I'm thinking of asking the workers to slot the drip edge at the hangar screws to allow the edge to be pushed back a bit, though I can't say how much closer the edge can be pushed back given the bottom kickout (bend). Maybe better to caulk the space.

In most places the eave shingles appear to be an acceptable length over the edge, except I can see in the distance at the rake it looks like it's covering too much of the gutter. Manufacturer says half an inch for eave with a drip edge, and 3/4" at rake with no drip edge.

dscn7470ed.jpg   dscn7465ed.jpg  
__________________

Last edited by D725A; 09-04-2012 at 07:43 PM.
D725A is offline  
 
Reply With Quote Quick reply to this message
Reply


Quick Reply
Message:
Options

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter DIY Home Repair Forum Replies Last Post
Colonial Gambrel Roof ventilation questions drewdin Roofing and Siding 7 08-22-2012 08:20 PM
Porch roof questions mikejurasw Roofing and Siding 2 06-14-2011 05:16 PM
Roof structure questions for Cathedral ceilings (pics) BKB94 Framing and Foundation 1 07-30-2009 06:01 AM
cathedral ceilings questions about roof support (pics) BKB94 Flooring 1 07-30-2009 06:00 AM
Flashing/drip edge on roof - questions & advice Westy Roofing and Siding 4 09-24-2007 07:37 PM