I am adding a utility room to my house now. The next addition I want is a master bedroom/bath/ WIC. Would I waste a lot of money if I do the bedroom now then come back later with the bath and WIC? The house is paid for and I am wanting just to pay for each project as I go.
It will most likely cost more overall to do it that way.
Everybody(excavator, foundation formers, carpenters, drywallers, roofers, electricians, etc.) will have to come back twice.
I am adding a utility room to my house now. The next addition I want is a master bedroom/bath/ WIC. Would I waste a lot of money if I do the bedroom now then come back later with the bath and WIC? The house is paid for and I am wanting just to pay for each project as I go.
The money you don't spend now can be invested or used elsewhere. Depending on the costs & benefits & risks of each choice it might make sense to wait.
I would plan on doing all the rough work at one time. Foundation work, framing, roof, siding, plumbing, heating, wiring and insulation. Now you can do the rest whenever you want.