Hi. I am in need of some advise. So during a recent home elevation, one side of my back porch started to separate. Forgive me if I mess up on the specific terms related to the framing, but from what I understand the facial board that our deck was attached to, was rotten and fell apart during the elevation so there is nothing there to hold that side of the porch to the back of the home? I also included a picture of the inside of my home where you can see the Separation of the same wall just from inside. Any advise on how one might remedy this situation?Name:  ImageUploadedByHome Repair1500136531.303019.jpg
Views: 20
Size:  60.3 KBName:  ImageUploadedByHome Repair1500136745.627432.jpg
Views: 20
Size:  45.2 KBName:  ImageUploadedByHome Repair1500136766.583868.jpg
Views: 21
Size:  35.4 KB
Name:  ImageUploadedByHome Repair1500136780.995765.jpg
Views: 20
Size:  75.9 KB


simonsx5 is offline  
 
Reply With Quote
Old 07-15-2017, 12:39 PM  
slownsteady
Administrator
HRT_ADMIN.png
 
slownsteady's Avatar
Join Date: Jun 2009
Location: Newton, NJ
Posts: 6,358
Liked 1128 Times on 934 Posts
Likes Given: 1844

Default

How much was your home elevated? And were the front posts of the deck anchored to the ground or were they free to move. Were they supported during the lift?


__________________
Learn something every day
---
SnS
slownsteady is offline  
 
Reply With Quote
Old 07-15-2017, 01:13 PM  
Snoonyb
Senior Member
Join Date: Sep 2006
Posts: 2,396
Liked 418 Times on 370 Posts
Likes Given: 1

Default

Welcome to the site.

The "facial board", is actually called a rim joist, and SNS is correct that the deck should have been supported and raised with the house.

For no other reason than the roof loads.

The simplest correction is to lift the deck, lever it back into place, level it and secure it with heavy metal angle brackets.
__________________
Illigitimas non-carborundum
Snoonyb is offline  
 
Reply With Quote
Old 07-15-2017, 01:53 PM  
simonsx5
Junior Member
 
simonsx5's Avatar
Join Date: Jul 2017
Posts: 16
Default

My home was elevated 2 foot. The original posts under the deck were simply wooden post concreted in the ground. Most of those were cut off at deck level and replaced with concrete blocks. (Picture below). The concrete blocks are still not anchored or attached to the home at all. The tie downs were installed under the home into the footing and wrapped around joists in random places. (Picture below)

Name:  ImageUploadedByHome Repair1500148284.283045.jpg
Views: 18
Size:  66.9 KBName:  ImageUploadedByHome Repair1500148405.699696.jpg
Views: 18
Size:  61.1 KB
simonsx5 is offline  
 
Reply With Quote
Old 07-15-2017, 01:54 PM  
simonsx5
Junior Member
 
simonsx5's Avatar
Join Date: Jul 2017
Posts: 16
Default

Snoony B- when you say lever it, are we talking like a ratchet strap?
simonsx5 is offline  
 
Reply With Quote
Old 07-15-2017, 01:55 PM  
simonsx5
Junior Member
 
simonsx5's Avatar
Join Date: Jul 2017
Posts: 16
Default

Sorry to be a pain, what type of metal brackets, and where would those said brackets go?
simonsx5 is offline  
 
Reply With Quote
Old 07-15-2017, 02:23 PM  
slownsteady
Administrator
HRT_ADMIN.png
 
slownsteady's Avatar
Join Date: Jun 2009
Location: Newton, NJ
Posts: 6,358
Liked 1128 Times on 934 Posts
Likes Given: 1844

Default

Have you been able to confirm the amount of rot involved? It sounds to my cynical ear, like something a contractor ( a disreputable one) might say if he was looking for an excuse. If there is rot, now would be the time to fix it and defend against future problems. If the board is not really rotted, it probably needs to be reinforced at this time because of the damage done to it when the deck pulled loose.
I don't think ratchet straps would be strong enough to raise a deck. You would have to jack up the lower end, and you may need cables to pull it back against the ledger. Then it can be fastened to the new ledger board. The supports under the lower spot may need to be shimmed to support the deck at the right height.
__________________
Learn something every day
---
SnS
slownsteady is offline  
 
Reply With Quote
Old 07-15-2017, 03:07 PM  
Snoonyb
Senior Member
Join Date: Sep 2006
Posts: 2,396
Liked 418 Times on 370 Posts
Likes Given: 1

Default

Quote:
Originally Posted by simonsx5 View Post
Snoony B- when you say lever it, are we talking like a ratchet strap?
Thanks, I had assumed they would have poured either a continuous stem wall foundation or placed a continuous CMU foundation.

How often do these CMU pilasters and hold downs occur across the length of the deck attachment?

The process involves some cribbing, bottle jacks and a couple of 4X6.

Set the first jacks 18" out from the rim joist/ledger and after you have it lifted pull all the nails used to attach it to the house. Attach a strap or cable to the deck joist and the other end with the ratchet to the house floor joists, or a support beam.
__________________
Illigitimas non-carborundum
Snoonyb is offline  
 
Reply With Quote
Old 07-15-2017, 07:22 PM  
simonsx5
Junior Member
 
simonsx5's Avatar
Join Date: Jul 2017
Posts: 16
Default

Ok. So my husband says that the CMU's are all different as far as spacing. We measured 2 on the very back and one measured 11' 3" between them and another measured 12' there are 2 tie downs both on each end of the porch. There are about 15 CMU's on the interior of the deck and they are spaced much closer. I have given more pictures below. The first one is the porch from the back. The second is the rim joist on the opposite side of the house that is not separating. Name:  ImageUploadedByHome Repair1500167936.736430.jpg
Views: 16
Size:  47.8 KB The third picture is what looks like the rim joist pushing out on the siding of the home. The last is how my general contractor added support, but it doesn't seem to be working and he doesn't want to go behind and fix what the foundation contractor messed up. He just wants to cover it up. I think we will try the suggestions so far and see if we can get it to come in some. Name:  ImageUploadedByHome Repair1500168014.329337.jpg
Views: 17
Size:  48.3 KBName:  ImageUploadedByHome Repair1500167844.421467.jpg
Views: 16
Size:  69.7 KBName:  ImageUploadedByHome Repair1500167875.083867.jpg
Views: 16
Size:  55.0 KB
simonsx5 is offline  
 
Reply With Quote
Old 07-15-2017, 07:23 PM  
simonsx5
Junior Member
 
simonsx5's Avatar
Join Date: Jul 2017
Posts: 16
Default

Sorry, my picture order got messed up.


simonsx5 is offline  
 
Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off


Similar Threads
Thread Thread Starter DIY Home Repair Forum Replies Last Post
Separation Between Carport & House Slab billhead1 Bricks, Masonry and Concrete 3 06-26-2012 01:23 AM
Foundation Separation xjryan Framing and Foundation 1 12-23-2011 02:19 AM
Brick separation repair laddie2 Bricks, Masonry and Concrete 5 09-09-2011 01:32 PM
Door frame separation sworth4937 Framing and Foundation 1 08-15-2009 01:35 PM
wall/floor separation jetster71 Framing and Foundation 8 04-21-2007 11:22 AM



Newest Threads