addition timelines

Discussion in 'General Home Improvement Discussion' started by lmg, Jan 3, 2013.

  1. Jan 3, 2013 #1

    lmg

    lmg

    lmg

    New Member

    Joined:
    Jan 3, 2013
    Messages:
    1
    Likes Received:
    0
    I am adding a utility room to my house now. The next addition I want is a master bedroom/bath/ WIC. Would I waste a lot of money if I do the bedroom now then come back later with the bath and WIC? The house is paid for and I am wanting just to pay for each project as I go.
     
  2. Jan 3, 2013 #2

    JoeD

    JoeD

    JoeD

    Well-Known Member

    Joined:
    Mar 16, 2006
    Messages:
    1,524
    Likes Received:
    273
    It will most likely cost more overall to do it that way.
    Everybody(excavator, foundation formers, carpenters, drywallers, roofers, electricians, etc.) will have to come back twice.
     
  3. Jan 3, 2013 #3

    Wuzzat?

    Wuzzat?

    Wuzzat?

    Well-Known Member Sponsor

    Joined:
    Jan 20, 2010
    Messages:
    2,471
    Likes Received:
    175
    The money you don't spend now can be invested or used elsewhere. Depending on the costs & benefits & risks of each choice it might make sense to wait.

    I guess a related concept is 'opportunity cost.'
     
  4. Jan 3, 2013 #4

    nealtw

    nealtw

    nealtw

    Contractor retired

    Joined:
    Nov 4, 2010
    Messages:
    23,890
    Likes Received:
    3,117
    I would plan on doing all the rough work at one time. Foundation work, framing, roof, siding, plumbing, heating, wiring and insulation. Now you can do the rest whenever you want.
     