    I want to know what is the curing period for 3 coats system stucco between coats.Our contractor wants to apply the brown coat after 3 days of puting the scratch coat. Is this right?
    Thank you,
     
    Last edited: Sep 23, 2010
  2. Sep 24, 2010 #2

    rory_88

    rory_88

    rory_88

    Member

    Joined:
    Oct 10, 2007
    Messages:
    9
    Likes Received:
    0
    I'm not sure and I will be interested to know the definitive answer. However, I'm going to hazard a guess that there is a chemical bond that is created between the three coats that depends on the coats curing together.
     
  3. Sep 25, 2010 #3

    CSmith

    CSmith

    CSmith

    Member

    Joined:
    Aug 30, 2010
    Messages:
    14
    Likes Received:
    0
    ThatÂ’s fine, letting each layer cure independently is key.
     
  4. Sep 25, 2010 #4

    rory_88

    rory_88

    rory_88

    Member

    Joined:
    Oct 10, 2007
    Messages:
    9
    Likes Received:
    0
    OK so my guess was wrong... glad someone else chimed in!
     