    OK...finally starting on my kitchen remodel!! Here are the things we'll be doing:

    demo
    new cabinets/countertops
    porcelain tile floor
    moving gas line for range
    moving plumbing for sink
    moving electrical for disposal / microwave
    paint
    removing soffits/patchwork

    Since I'm playing general contractor for this...can you guys give some tips on how to order the projects?

    I have a general idea...but there are some grey areas for me as well. In what order should these different tasks be handled?

    Any other tips or info for a first time homeowner/kitchen remodeler would be helpful.

    Thanks guys.
     
  2. Aug 10, 2010 #2

    universalremodeling

    universalremodeling

    universalremodeling

    Member

    Joined:
    Aug 3, 2010
    Messages:
    8
    Likes Received:
    0
    I would suggest you first move your kitchen things .
     
  3. Aug 10, 2010 #3

    BrianKiernan

    BrianKiernan

    BrianKiernan

    Active Member

    Joined:
    Aug 10, 2010
    Messages:
    42
    Likes Received:
    0
    This is the order

    1. Demo
    2. New Framing Replace Window If Any
    3. Rough Plumbing
    4. Rough Electrical
    5. Rough HVAC
    6. Rough Inspections
    7. Insulation
    8. Insulation Inspection
    9. Sheetrock & Tape
    10. Prime all walls and paint ceiling, do first coat on walls only
    11. Install Floor
    12. Install Cabinet and trim
    13. Paint all trim and then final coat walls
    14.Install counter top
    15. Trim out electrical and plumbing plus HVAC
    16.Install Appliances
    17.Enjoy New Kitchen :)
     