    We are gonna have wood floors sanded and redone, some electrical done(new fixtures, fans, ec), paint the walls and ceilings, and get some new appliances in the kitchen.. What is the best order to these things in?

    We have been told to get the floors done 1st to avoid the dust issue on fairly fresh painted walls...
     
  2. Oct 28, 2009 #2

    thisdmnhouse

    thisdmnhouse

    thisdmnhouse

    Owner, This D*mn House

    Joined:
    Oct 7, 2009
    Messages:
    7
    Likes Received:
    0
    I'd get the electrical done before anything else. You wouldn't want someone tearing up your just painted walls to get access to wiring. Likewise for the floor.

    Not to mention that electrical is a safety issue (and you HAVE to have lights) where the floors and walls are aesthetic changes. Safety first.:)

    Get the appliances last. That way, you don't have to worry about getting paint or dust on them OR worry about where you're moving them to while you work on the floor.
     
  3. Oct 28, 2009 #3

    kok328

    kok328

    kok328

    Well-Known Member

    Joined:
    Nov 20, 2007
    Messages:
    2,755
    Likes Received:
    249
    My opinion (it's not always black & white):
    1. electrical
    2. sand the floors
    3. wipe down the walls
    4. painting
    5. finish the floors
    6. appliances
     