Contractor's kickout flashing: right, wrong, or just ugly?

House Repair Talk

Help Support House Repair Talk:

This site may earn a commission from merchant affiliate links, including eBay, Amazon, and others.

BNDYI

New Member
Joined
Nov 5, 2016
Messages
2
Reaction score
1
I had some stucco work done and the contractor recommended adding kickout flashing which I knew was the right thing to do, but it was installed differently than I expected. It comes out in front of the stucco trim instead of to the side of it. It's an eyesore. If I'd done it I would have installed the flashing 3" farther up the roof so the corner of the last shingle was in the corner of the flashing and the flashing would come out of the side of the trim instead of coming out of the front of it. Is the way it's done wrong? Is the way I want it done wrong? Would I have any argument for telling the contractor to redo it?

Web Kickout 2.jpg

Web Kickout.JPG
 
Last edited:
Actually you are correct, he could have done the "kick-out" by simply tucking the "L" metal under the existing flashing and forming the turn to deflect the runoff into the gutter.

To the bigger point, in that not using "Z Bar may be aesthetically appealing now, but a problem to seal in successive roof applications.
 
#1, I would have used black, not silver.
#2, I would have installed in under the next to last shingle above whatever he used for that outside corner for a few reasons.
Less visible, it would direct water away from the bottom of that outside corner
 
Thanks for the responses. I will be replacing the roof in the next couple of years and at that time I will cut the stucco away from the roof and install Z bar flashing. For now I'd like to get this project wrapped up. This project started out as cutting and replacing the stucco trim for windows, but grew when rot was discovered. I was able to talk the contractor out of the $$$ he was charging me for 3 flashings, as it was part of the walls he was charging me for separately. However I was not able to convince him that his hourly rate was too high. I usually do things myself, this is the first time I've hired someone for a house project. I learned a few lessons; as soon as the scope of the project grew beyond the original estimate I should have done these three things:

1-I should have asked what the hourly rate was.
2-I should have asked how many hours they expected.
3-I should have examined how much work I could do myself.
 
4. Cheapest price is the cheapest job. Next time ask yourself, am I paying enough to fix it correctly?
 
Thanks for the responses. I will be replacing the roof in the next couple of years and at that time I will cut the stucco away from the roof and install Z bar flashing. For now I'd like to get this project wrapped up. This project started out as cutting and replacing the stucco trim for windows, but grew when rot was discovered. I was able to talk the contractor out of the $$$ he was charging me for 3 flashings, as it was part of the walls he was charging me for separately. However I was not able to convince him that his hourly rate was too high. I usually do things myself, this is the first time I've hired someone for a house project. I learned a few lessons; as soon as the scope of the project grew beyond the original estimate I should have done these three things:

1-I should have asked what the hourly rate was.
2-I should have asked how many hours they expected.
3-I should have examined how much work I could do myself.

You will want a step flashing when you do the roof.
 
Back
Top