What's the rough timing breakdown, from excavation to the day you can start framing the house walls, to build a slab-on-grade foundation for a simple master bedroom+bathroom addition? Assume an experienced crew of (5?) + plumber and dry summer weather in N. CA.
I've cobbled this together from online sources but know it's waaaay off:
Excavation: 1-2 days
Footings: 2 days
Ground plumbing: 2 days + inspection
Pour gravel bed in foundation, lay vapor barrier, mesh: no idea
Pour foundation: 1 day
Cure concrete: 7 days
Backfill: 1 day
Total: 16+ days???
Many thanks.