user 62771
Member
- Joined
- Feb 1, 2024
- Messages
- 8
- Reaction score
- 0
My crawl space has four continuous strip footings as a base for all the (46) 4x6 posts which hold (15) 4x6 beams in position for my subfloor riding atop the beams. There's (2) 42 ft. length concrete strip footings & (2) 21 ft. length. strip footings.
The first of two 42 ft strip footings, runs a little short on each end. The very last post at the end of either side of the first strip footing doesn't provide a good stable base for the 4x6 post, hence the reason why I want to extend the strip footing.
(The good news is): the beams & posts are only 28.5 inches on center running the length of the strip footings. There's fifteen (15) 4x6 beams, forty six (46) total posts in my 1000 sq ft. And the beams run perpendicular to the strip footings. There are no floor sags, cracks in walls, door frames, doors or windows inoperative/warped, floor is level throughout above 4x6 beams in home, or any other signs of problems.
1. I need to extend that strip footing, which is already reinforced with half inch rebar. Home is built in 1978.
2. I need to dig down in front of the strip footing for a compacted Rock base of about 8 to 12 in deep.
3. The strip footing is from grade, 6 in tall by 12 in wide. Then build a form, where I'm going to pour the concrete to extend strip footing, to enable good solid concrete surface for 4x6 post.
3A. I should use 2500 to 3,000 psi concrete. And I should drill into end of existing strip footing, to reinforce with rebar, as well as place rebar where I'm going to pour the concrete within the form. Tie the rebar together.
4. Clean the end of the concrete surface area of the strip footing of soil, so adhesion from new concrete will grab old concrete and bond together.
5. Using Bottle Jack, raise area up by nominal amount, like ⅛ to ¼ inch against 4x6 beam, remove 4x6 post, so concrete work can be accomplished.
6. Pour Concrete, screed top surface of form/concrete.
7. Let cure for a few days.
8. Remove form, and reposition posts in place, with plastic or shingle between lumber & concrete, then lower down, using in position Bottle Jack onto post.
9. Done.
If I left out a step, got my steps (1, 2 3, etc.) out of order, make corrections & specifics on what I missed, etc. & should do differently or instead. Thanks for your help. Dan
The first of two 42 ft strip footings, runs a little short on each end. The very last post at the end of either side of the first strip footing doesn't provide a good stable base for the 4x6 post, hence the reason why I want to extend the strip footing.
(The good news is): the beams & posts are only 28.5 inches on center running the length of the strip footings. There's fifteen (15) 4x6 beams, forty six (46) total posts in my 1000 sq ft. And the beams run perpendicular to the strip footings. There are no floor sags, cracks in walls, door frames, doors or windows inoperative/warped, floor is level throughout above 4x6 beams in home, or any other signs of problems.
1. I need to extend that strip footing, which is already reinforced with half inch rebar. Home is built in 1978.
2. I need to dig down in front of the strip footing for a compacted Rock base of about 8 to 12 in deep.
3. The strip footing is from grade, 6 in tall by 12 in wide. Then build a form, where I'm going to pour the concrete to extend strip footing, to enable good solid concrete surface for 4x6 post.
3A. I should use 2500 to 3,000 psi concrete. And I should drill into end of existing strip footing, to reinforce with rebar, as well as place rebar where I'm going to pour the concrete within the form. Tie the rebar together.
4. Clean the end of the concrete surface area of the strip footing of soil, so adhesion from new concrete will grab old concrete and bond together.
5. Using Bottle Jack, raise area up by nominal amount, like ⅛ to ¼ inch against 4x6 beam, remove 4x6 post, so concrete work can be accomplished.
6. Pour Concrete, screed top surface of form/concrete.
7. Let cure for a few days.
8. Remove form, and reposition posts in place, with plastic or shingle between lumber & concrete, then lower down, using in position Bottle Jack onto post.
9. Done.
If I left out a step, got my steps (1, 2 3, etc.) out of order, make corrections & specifics on what I missed, etc. & should do differently or instead. Thanks for your help. Dan
Last edited: